United States v. Utah Construction & Mining Co.
384 U.S. 394 (1966)
Premium Feature
Subscribe to Lexplug to listen to the Case Podcast.
Rule of Law:
Factual findings properly made by an administrative board on a claim 'arising under the contract' are binding on the parties in a subsequent court action for breach of contract. This preclusive effect prevents the relitigation of facts already decided, even when the board could not grant the relief sought in the court action, such as monetary damages for breach.
Facts:
- In March 1953, Utah Construction & Mining Company (Utah) entered into a contract with the Atomic Energy Commission (AEC) to construct a facility.
- During the project, Utah encountered 'float rock' while excavating, which it claimed was a 'changed condition' under the contract that increased its costs and caused delays.
- Utah also alleged that inadequate specifications and drawings provided by the Government for 'shield windows' constituted another 'changed condition' that caused delays.
- Separately, Utah used concrete aggregate from a government stockpile and discovered it was of poor quality, leading to understrength concrete and work suspensions.
- The contract contained a standard 'Disputes' clause (Article 15) providing that all disputes concerning questions of fact 'arising under this contract' would be decided by a contracting officer, with a right of appeal, and that the administrative decision would be 'final and conclusive'.
Procedural Posture:
- Utah Construction & Mining Co. (Utah) filed claims for equitable adjustments and time extensions with the Atomic Energy Commission's (AEC) contracting officer, who denied them.
- Utah appealed to the AEC Advisory Board of Contract Appeals (the Board).
- The Board made factual findings regarding the causes of delays but denied most monetary relief, ruling that claims for breach of contract and delay damages were outside its jurisdiction.
- Utah then sued the United States in the U.S. Court of Claims, seeking damages for breach of contract.
- The Court of Claims held that breach of contract claims were not subject to the Disputes clause and that the Board's factual findings were not binding, ordering a de novo trial on the facts.
- The United States petitioned the Supreme Court of the United States for a writ of certiorari, which was granted.
Premium Content
Subscribe to Lexplug to view the complete brief
You're viewing a preview with Rule of Law, Facts, and Procedural Posture
Issue:
Are administrative factual findings made on a claim 'arising under this contract' (e.g., for a time extension) final and conclusive in a subsequent court action for breach of contract, even if the administrative board lacked jurisdiction to award breach of contract damages?
Opinions:
Majority - Mr. Justice White
Yes, administrative factual findings made on a claim 'arising under this contract' are final and conclusive in a subsequent court action for breach of contract. First, the Court held that the phrase 'arising under this contract' limits the jurisdiction of administrative boards to claims where a specific contract clause provides for relief (e.g., an equitable adjustment for 'changed conditions'). It does not extend to 'pure' breach of contract claims for which the contract provides no remedy, such as claims for unreasonable delay damages. This interpretation is based on a long and uniform history of judicial and administrative construction upon which the contracting parties relied. Second, and dispositively for the issue at hand, the Court held that when an administrative board properly makes factual findings on a matter within its jurisdiction (like determining the cause of a delay for a time extension request), those findings are binding on the parties in a subsequent court action for breach of contract. The finality required by the Disputes clause and the Wunderlich Act, along with general principles of collateral estoppel, prevents a party from relitigating the same factual issues simply by recasting the claim as a breach of contract in a different forum. This avoids duplicative evidentiary hearings and encourages full disclosure at the administrative level.
Analysis:
This decision establishes the foundational 'Utah doctrine' in government contract law, creating a bifurcated system for resolving disputes. Claims 'arising under the contract' must be adjudicated through the administrative process, while pure breach of contract claims must be brought in court. Crucially, the ruling prevents fragmented litigation by giving administrative fact-finding a preclusive (collateral estoppel) effect in subsequent court proceedings. This solidifies the role of Boards of Contract Appeals as the primary and final fact-finders for matters within their jurisdiction, promoting judicial economy and forcing contractors to fully litigate factual issues at the administrative stage or risk being bound by adverse findings.

Unlock the full brief for United States v. Utah Construction & Mining Co.