United States v. Spearin

Supreme Court of the United States
39 S. Ct. 59, 1918 U.S. LEXIS 1700, 248 U.S. 132 (1918)
ELI5:

Rule of Law:

When a party furnishes detailed plans and specifications for a contractor to follow, there is an implied warranty that those plans are adequate and suitable for the particular purpose. The contractor is not responsible for damages resulting from defects in the owner-provided specifications.


Facts:

  • The United States Government contracted with Spearin to build a dry-dock at the Brooklyn Navy Yard according to plans and specifications prepared by the Government.
  • The Government's plans required Spearin to relocate a 6-foot brick sewer that intersected the construction site, prescribing its specific dimensions, materials, and location.
  • Spearin relocated the sewer in full compliance with the Government's specifications, and the Government accepted the completed section as satisfactory.
  • Approximately one year later, heavy rain and a high tide caused the relocated 6-foot sewer to break from internal pressure, flooding the dry-dock excavation.
  • An investigation revealed that the pressure was caused by an unknown dam within a connecting 7-foot sewer, which was not shown on the Government's plans or known to its officials.
  • Although Government officials knew the area had a history of sewer overflows, this information was not communicated to Spearin.
  • Spearin notified the Government that he would not resume work unless the Government assumed responsibility for the damage and remedied the unsafe sewer conditions.
  • The Government insisted that Spearin was responsible for the repairs and, after a fifteen-month dispute, annulled the contract.

Procedural Posture:

  • Spearin sued the United States in the Court of Claims, seeking damages for breach of contract.
  • The Court of Claims (the court of first instance) entered a judgment in favor of Spearin for $141,180.86.
  • Both the United States Government (as appellant) and Spearin (as cross-appellant) appealed the judgment of the Court of Claims to the Supreme Court of the United States.

Locked

Premium Content

Subscribe to Lexplug to view the complete brief

You're viewing a preview with Rule of Law, Facts, and Procedural Posture

Issue:

Does the government, by providing a contractor with detailed plans and specifications for a construction project, implicitly warrant that those plans, if followed, will result in a satisfactory and adequate outcome, thus making the government liable for damages resulting from defects in those plans?


Opinions:

Majority - Mr. Justice Brandeis

Yes. When the government provides detailed plans and specifications for a contractor to follow, it implicitly warrants their adequacy, and the contractor is not responsible for the consequences of defects in those plans. The court reasoned that while a contractor generally assumes the risk of unforeseen difficulties, this rule does not apply when the contractor is required to follow plans prepared by the owner. The detailed specifications for the sewer relocation constituted an implied warranty that the sewer, if constructed as specified, would be adequate. This warranty is not overcome by general contract clauses requiring the contractor to examine the site or check the plans. The government's failure to provide adequate plans, coupled with its refusal to take responsibility for the resulting failure, constituted a material breach of the contract, which justified Spearin's refusal to continue the work and entitled him to damages for the breach.



Analysis:

This case established the landmark 'Spearin Doctrine,' a fundamental principle in construction and government contract law. The decision shifts the risk of design defects from the contractor to the owner who provides the design specifications. This doctrine protects contractors who properly execute the owner's plans, ensuring they are not held liable for failures caused by a faulty design. It has profoundly influenced contract drafting and litigation, creating a clear line of responsibility and serving as a key defense for contractors against claims of defective workmanship when the true fault lies in the owner-provided plans.

G

Gunnerbot

AI-powered case assistant

Loaded: United States v. Spearin (1918)

Try: "What was the holding?" or "Explain the dissent"