Page v. Structural Wood Components, Inc.

Texas Supreme Court
102 S.W.3d 720, 2003 Tex. LEXIS 42, 46 Tex. Sup. Ct. J. 561 (2003)
ELI5:

Rule of Law:

For the purpose of perfecting a mechanic's lien on retained funds under the Texas Property Code, the "work" under an original construction contract is deemed completed upon that contract's termination or abandonment. The 30-day statutory period for a subcontractor to file a lien affidavit begins on the date of termination, not on the date the overall project is eventually finished by replacement contractors.


Facts:

  • In 1997, Herman C. Page hired Mark Sepolio as the general contractor for a building remodeling and expansion project.
  • Sepolio hired several subcontractors, including Structural Wood Components, Inc. (Structural Wood), to provide labor and materials.
  • Structural Wood fully performed its work under its subcontract by mid-March, 1998.
  • Sepolio failed to pay Structural Wood in full for its labor and materials.
  • Following a dispute over the work and a request for additional funds, Page terminated his contract with Sepolio on April 14, 1998.
  • Page then hired six new contractors to complete the project.
  • The replacement contractors finished the construction originally contemplated under Sepolio's contract on July 21, 1998.

Procedural Posture:

  • Structural Wood filed an affidavit claiming a lien on Page's property on May 15, 1998, thirty-one days after Page terminated Sepolio's contract.
  • Structural Wood filed suit against Page and Sepolio in the trial court to foreclose on its lien.
  • Following a bench trial, the trial court found in favor of Structural Wood, concluding the work was completed on July 21, 1998, and held Page and Sepolio jointly and severally liable.
  • Page, as appellant, appealed to the court of appeals.
  • The court of appeals reformed the trial court's judgment but affirmed the personal judgment against Page, agreeing that the work was completed when the project was finished in July 1998.
  • Page, as petitioner, then sought review from the Supreme Court of Texas.

Locked

Premium Content

Subscribe to Lexplug to view the complete brief

You're viewing a preview with Rule of Law, Facts, and Procedural Posture

Issue:

Does the termination of an original construction contract by the property owner constitute 'completion of the work' under Texas Property Code § 53.103, thereby starting the 30-day period for a subcontractor to file a lien affidavit?


Opinions:

Majority - Chief Justice Phillips

Yes, the termination of an original construction contract constitutes 'completion of the work' for purposes of the 30-day lien filing deadline. The Texas Property Code defines 'work' as that performed 'under an original contract.' When a contract is terminated, no further work can be contemplated or performed under that specific contract, so the work under it is complete. The court's reasoning is supported by legislative history indicating an intent to tie retainage requirements to individual contracts to prevent indefinite payment delays, which would harm both original contractors and subcontractors awaiting payment from retained funds. Furthermore, a statutory disclosure statement for residential projects explicitly lists 'termination, or abandonment of the contract' as an event triggering the 30-day retainage period, providing guidance on the legislature's interpretation of completion.


Dissenting - Justice Enoch

No, the 30-day period should not begin until the work originally contemplated is actually finished, regardless of who completes it. The statute unambiguously defines 'completion' as the 'actual completion of the work,' and this language should be construed literally. The majority improperly adds 'termination' and 'abandonment' to a clear legislative definition. The purpose of mechanic's lien statutes is to protect subcontractors, who may have no way of knowing that the general contractor's contract has been terminated. Tying the deadline to the project's actual completion ensures protection for all subcontractors, whereas the majority's rule creates a hardship and places an unfair monitoring burden on the very parties the statute is meant to protect.



Analysis:

This decision clarifies a critical timing requirement for perfecting mechanic's liens in Texas, establishing that a contract's termination is a 'completion' event. It shifts the risk from owners and general contractors, who benefit from finality and prompt payment, to subcontractors, who must now diligently monitor the contractual relationship between the owner and general contractor. Subcontractors can no longer rely on the physical progress or completion of the entire project to determine their lien-filing deadline. This precedent emphasizes a contract-centric view of 'completion' over a project-centric one, potentially shortening the filing window for subcontractors on projects where the general contractor is replaced.

🤖 Gunnerbot:
Query Page v. Structural Wood Components, Inc. (2003) directly. You can ask questions about any aspect of the case. If it's in the case, Gunnerbot will know.
Locked
Subscribe to Lexplug to chat with the Gunnerbot about this case.

Unlock the full brief for Page v. Structural Wood Components, Inc.