Northrop Grumman Computing Systems, Inc. v. United States
2015 WL 1546248, 120 Fed.Cl. 460 (2015)
Premium Feature
Subscribe to Lexplug to listen to the Case Podcast.
Rule of Law:
Expectation damages for a breach of contract are intended to place the non-breaching party in the position it would have occupied had the contract been fully performed, not in a better position. A plaintiff cannot recover such damages if a third-party financing arrangement has already provided the plaintiff with the full anticipated value and profit of the contract, as the plaintiff has suffered no actual financial harm.
Facts:
- On September 24, 2004, the Bureau of Immigration and Customs Enforcement (ICE) awarded a delivery order to Northrop Grumman Computing Systems, Inc. (Northrop) to lease surveillance software for a one-year base period with three optional one-year extensions.
- Northrop delivered the software, and ICE paid Northrop $900,000 for the base year of the contract.
- To finance the transaction, Northrop entered into a Purchase and Assignment Agreement with a third-party company, ESCgov.
- Under this agreement, Northrop assigned its right to receive all future payments from ICE to ESCgov in exchange for an upfront payment of $3,296,093 from ESCgov.
- This upfront payment from ESCgov included Northrop's entire anticipated profit ($191,571) for the base year and all three option years.
- The financing agreement stipulated that if ICE did not exercise its renewal options, Northrop would not be liable to ESCgov for any lost profits or other costs.
- On September 30, 2005, ICE notified Northrop that it would not exercise the first one-year option due to a lack of funds.
Procedural Posture:
- Northrop Grumman filed a claim with the government contracting officer, which was denied.
- Northrop Grumman filed a complaint for breach of contract against the United States in the U.S. Court of Federal Claims (the trial court).
- The Court of Federal Claims initially granted the government's motion to dismiss for lack of jurisdiction based on inadequate notice in Northrop's claim.
- Northrop Grumman (appellant) appealed the dismissal to the U.S. Court of Appeals for the Federal Circuit.
- The Federal Circuit reversed the dismissal, finding the notice was adequate and Northrop was the proper party, and remanded the case back to the Court of Federal Claims.
- On remand, the United States (defendant) filed a motion for summary judgment on the issue of damages.
Premium Content
Subscribe to Lexplug to view the complete brief
You're viewing a preview with Rule of Law, Facts, and Procedural Posture
Issue:
Can a contractor recover expectation damages from the government for an alleged breach of an option contract when the contractor has already been paid its full anticipated profit for the entire contract term by a third-party financing company?
Opinions:
Majority - Allegra, J.
No. A contractor cannot recover expectation damages when it has already been paid its full anticipated profit and suffered no actual financial harm. The purpose of expectation damages is to give the injured party the benefit of the bargain, not to provide a windfall. Here, Northrop entered a financing agreement with ESCgov and received an upfront payment that included its total anticipated profit for the entire potential life of the contract. Because Northrop has already reaped the full benefit of the bargain it negotiated, it is in the same financial position it would have been in had ICE fully performed. Any further payments from ICE for the unexercised options would have been assigned to ESCgov, not paid to Northrop. As Northrop cannot identify any way it was financially harmed by ICE's decision not to exercise the options, it is not entitled to damages.
Analysis:
This decision reinforces the fundamental principle that contract damages are compensatory, not punitive, and that a plaintiff must prove actual harm to recover. The court looked beyond the formal contract between Northrop and the government to the economic reality of the situation, including third-party financing. This case serves as a precedent that complex financing structures, such as assigning rights to payment, can extinguish a party's ability to claim damages for a breach if those structures effectively insulate the party from financial loss. Future government contractors must be aware that how they finance a contract can directly impact their ability to recover damages if the government fails to exercise options.