MidAmerica Construction Management, Inc. v. MasTec North America, Inc.
2006 U.S. App. LEXIS 3022, 2006 WL 291663, 436 F.3d 1257 (2006)
Rule of Law:
In private-sector construction subcontracts, “pay-if-paid” clauses that clearly and unequivocally make a general contractor's obligation to pay a subcontractor contingent upon the owner's payment to the general contractor are enforceable under both Texas and New Mexico law, thereby shifting the risk of owner non-payment to the subcontractor.
Facts:
- PathNet, Inc. hired Renegade of Idaho, Inc. to assist in constructing portions of a fiber optic network in New Mexico and Texas.
- MasTec North America, Inc. subsequently purchased Renegade of Idaho, Inc.
- On January 31, 2001, MasTec and Renegade (Contractors) hired MidAmerica Construction Management, Inc. (Subcontractor) as a subcontractor to help install buried conduit for the fiber optic line.
- MidAmerica began performing work under the written Subcontract Agreement.
- MasTec and Renegade made an initial payment of approximately $127,000 to MidAmerica in March 2001 for work performed in January and February of that year.
- In April 2001, PathNet filed for bankruptcy.
- Following PathNet's bankruptcy filing, MasTec and Renegade refused to make any further payments to MidAmerica, asserting they had not received payment from PathNet for the work MidAmerica performed.
Procedural Posture:
- In November 2003, MidAmerica Construction Management, Inc. (Plaintiff) brought suit against MasTec North America, Inc. and Renegade of Idaho, Inc. (Defendants) in the United States District Court for the Western District of Oklahoma, contending Defendants owed it approximately $1.9 million for work performed.
- The District Court denied MidAmerica's motion for partial summary judgment.
- The District Court granted MasTec and Renegade's counter-motion for summary judgment on all MidAmerica's claims, holding that a provision in the Subcontract Agreement constituted an unambiguous and enforceable "pay-if-paid" clause under either New Mexico or Texas law.
- The District Court further found that a "termination clause" in the Subcontract Agreement also barred MidAmerica's claims for breach of contract.
- MidAmerica appealed the District Court’s order and judgment to the United States Court of Appeals for the Tenth Circuit (Appellant is MidAmerica; Appellees are MasTec and Renegade).
Premium Content
Subscribe to Lexplug to view the complete brief
You're viewing a preview with Rule of Law, Facts, and Procedural Posture
Issue:
Does a construction subcontract clause stating that “all payments to Subcontractor by Contractor are expressly contingent upon and subject to receipt of payment for the work by Contractor from Owner” constitute an enforceable “pay-if-paid” clause under Texas and New Mexico law, thereby making the owner’s payment to the general contractor a condition precedent to the general contractor’s obligation to pay the subcontractor?
Opinions:
Majority - Ebel, Circuit Judge
Yes, the construction subcontract clause stating that "all payments to Subcontractor by Contractor are expressly contingent upon and subject to receipt of payment for the work by Contractor from Owner" constitutes an enforceable "pay-if-paid" clause under both Texas and New Mexico law, making the owner's payment to the general contractor a condition precedent to the general contractor's obligation to pay the subcontractor. The court affirmed the district court's grant of summary judgment to Defendants MasTec and Renegade. The court found that the Subcontract Agreement contained clear conditional language, specifically the phrases "expressly contingent upon" and "subject to," which are indicative of an intent to create a condition precedent rather than merely a timing mechanism for payment (a "pay-when-paid" clause). Under Texas law, drawing from Gulf Construction Co. v. Self, such conditional language clearly signals an intent for a condition, and the court found the Subcontract Agreement's language sufficiently clear to create a "pay-if-paid" clause. The court also noted that the general weight of authority, including the reasoning in Thomas J. Dyer Co. v. Bishop International Engineering Co., supports enforcing such clauses when the intent to shift credit risk is clearly expressed. For New Mexico law, lacking direct precedent, the court looked to the general trend of authority and concluded that New Mexico courts would likely enforce a clearly drafted "pay-if-paid" clause. The court rejected arguments that New Mexico's Retainage Act implied a public policy against such clauses, noting its focus on timing rather than outright prohibition, and observed the absence of specific antiwaiver provisions in New Mexico's mechanic's lien laws or statutory bans on conditional payment provisions seen in other states. The court also held that a single partial payment made by the Defendants to Plaintiff did not create an ambiguity in the contract or establish an intent to waive the "pay-if-paid" clause, as the contract was unambiguous under Texas law, and post-formation conduct wouldn't create ambiguity under New Mexico law. Finally, the court found additional support for its interpretation in a "termination clause" within the Subcontract Agreement, which broadly stipulated that if the primary contract was terminated, suspended, or delayed for any reason, the subcontractor's remedy would generally be to seek recovery from the owner, not the contractor, further indicating the parties' intent to shift the risk of owner non-payment to the subcontractor.
Analysis:
This case provides significant clarity on the enforceability and interpretation of "pay-if-paid" clauses in private construction subcontracts within the Tenth Circuit, particularly under Texas and New Mexico law. It underscores the critical importance of clear and unambiguous contractual language in allocating the risk of owner non-payment, affirming that courts will enforce such risk-shifting provisions if plainly stated. The court's approach to determining state law in the absence of direct precedent, by examining general trends and legislative intent, offers valuable guidance for future cases involving contract interpretation under diversity jurisdiction. This ruling reinforces that subcontractors must exercise extreme caution and diligence when entering into agreements with "pay-if-paid" provisions, as these clauses can effectively preclude payment from the general contractor if the project owner defaults.
