J. Weingarten, Inc. v. Northgate Mall, Inc.
404 So. 2d 896 (1981)
Premium Feature
Subscribe to Lexplug to listen to the Case Podcast.
Rule of Law:
Under Louisiana law, specific performance is the preferred remedy for a breach of contract, but a court may withhold it in exceptional cases where the cost of performance is greatly disproportionate to the damages caused, performance is no longer in the obligee's interest, or it would have a substantial negative effect on the interests of third parties.
Facts:
- In 1968, J. Weingarten, Inc. leased space for a grocery store from Northgate Mall, Inc.
- The lease agreement limited Northgate's right to construct additional buildings in the common parking area and guaranteed a specific parking space-to-floor space ratio.
- In early 1978, Northgate planned a major expansion that exceeded its contractual rights by consuming over 100,000 square feet of the parking area, far more than the 39,375 square feet permitted.
- Negotiations between Weingarten and Northgate for a mutual modification of the lease to allow both parties to expand their respective premises failed to result in a written agreement.
- In February 1979, despite Weingarten's formal objections and threats of legal action, Northgate began construction of the $4 million expansion building in the contractually protected parking area.
Procedural Posture:
- J. Weingarten, Inc. sued Northgate Mall, Inc. in a Louisiana trial court, seeking preliminary and permanent injunctive relief.
- The trial court issued a temporary restraining order but subsequently dissolved it and denied Weingarten's motion for a preliminary injunction, finding no irreparable harm.
- Weingarten did not appeal or seek supervisory writs from the denial of the preliminary injunction.
- After a trial on the merits, which occurred after the new building was virtually complete, the trial court denied the permanent injunction.
- Weingarten, as appellant, appealed to the Louisiana Court of Appeal.
- The Court of Appeal reversed the trial court's decision, finding the breach caused irreparable harm and ordering Northgate, as appellee, to demolish the offending portion of the building.
- Northgate, as applicant, sought and was granted review by the Supreme Court of Louisiana.
Premium Content
Subscribe to Lexplug to view the complete brief
You're viewing a preview with Rule of Law, Facts, and Procedural Posture
Issue:
Does a court have the discretion to deny specific performance as a remedy for a breach of a commercial lease when that performance would require the destruction of a multi-million dollar building, the cost is greatly disproportionate to the harm suffered, and it would negatively impact innocent third parties?
Opinions:
Majority - Dennis, Justice
Yes, a court has discretion to deny specific performance under such circumstances. While Louisiana law prefers specific performance over damages for breach of contract, it is not an absolute right. A court may withhold this remedy when its disadvantages outweigh its advantages. Here, ordering the destruction of a completed $4 million building would be a grossly disproportionate remedy for the harm Weingarten suffered, which was a reduction in customer parking. The court weighed the immense economic and energy waste of demolition, the substantial harm to innocent third-party tenants in the new building, and the negative impact on the mortgage lender against Weingarten's contractual right. Concluding that the cost and third-party harm were exceptionally high compared to the actual damage, the court held that specific performance was inappropriate and that monetary damages were the proper remedy.
Concurring - Lemmon, Justice
Yes, the court correctly denied specific performance at this advanced stage of the litigation. However, this situation arose because the trial court improperly denied Weingarten's initial request for a preliminary injunction when construction began. At that early point, the equities favored Weingarten, and the blatant contract violation should have been stopped. Because injunctive relief was denied then, and Weingarten did not seek review of that ruling, the construction was completed, and the rights of innocent third parties (new tenants, mortgage holders) became involved, complicating the remedy and making the harsh measure of demolition inequitable now.
Analysis:
This case establishes a crucial judicial check on the remedy of specific performance in Louisiana's civilian legal system. It affirms that while specific performance is the preferred remedy, it is not absolute and is subject to a balancing test weighing fairness and practicality. The decision empowers courts to avoid economically wasteful and draconian outcomes by considering factors beyond the mere contractual breach, such as the proportionality of the remedy and its impact on third parties. This creates a more flexible, equitable approach but may reduce certainty for parties who expect strict enforcement of their bargained-for rights, especially in cases of willful breach.

Unlock the full brief for J. Weingarten, Inc. v. Northgate Mall, Inc.